SMRC, WA
In May 2006, RDT was successfully awarded the contract to design, install and commission a new MRF facility for Southern Metropolitan Regional Council in Perth. SMRC is an amalgamation of 9 local councils. The facility operates at 25 tph, processing approximately 1000 tonnes of waste per week.
Project Duration: 28 weeks - Plant Operational July 2007
Major Equipment utilized in the new MRF:
- Double Deck OCC and ONP Screens
- Optical Plastic Sorters x 3
- Glass Sorting System
- Overbelt magnet
- Vibratory Feeder
- Dual Waste Packer
- Plastic/Steel/Aluminium Baler
- Eddy Current
- Glass Fines Blower System
- Various Conveyors
- Sort Platforms, stairs and walkways
Role: Principal Contractor